Incoming Invoices
Compare what a subcontractor invoices with what it should be allowed to invoice under your rates.
Requirements
- Active connection to the subcontractor
- Purchase rate or dated terms maintained
- Delegated shifts in the period
Create target costs
On the Payables tab in Invoicing, “Create from delegated shifts” creates a draft. The server collects all shifts delegated to this subcontractor in the period and creates one target item per shift, plus separate premium items.
The basis is scheduled minutes, not clocked times. The actual clock-in and clock-out times are held by the subcontractor and are deliberately not visible to you.
If a purchase rate is missing, the draft stops with a notice instead of calculating with zero. If dated terms are maintained and a shift date is not covered by any of them, the entire draft also fails instead of showing a partial target.
If a different purchase rate was agreed in a request, it applies to the shifts in that request and takes precedence over the stored rate. Premiums remain as agreed.
Record actual values
When the invoice arrives, enter the invoice number, issue date, net amount, tax rate, and due date. The system calculates tax, gross amount, and the deviation from the target.
The deviation never blocks the process. It is shown as a traffic light: green at zero, yellow below five Euro, and red above that. You decide whether a deviation is acceptable.
An incoming invoice moves through Draft, Reconciled, and Paid. It cannot move directly from Draft to Paid. Reconciliation is mandatory. Canceled is final.

Purchase volume and margin
The upper block shows target, actual, and open amounts for each subcontractor over a period. Open can be negative if more was invoiced within the window than was delegated.
Important for Controlling: Only the actual value affects the margin, not the target. If incoming invoices are not recorded, the margin will therefore appear too high.
The window uses the issue date of the incoming invoice, not the service period. A May invoice recorded in June therefore shifts the margin into June.
Related
- SubcontractorsRequest that partner companies cover shifts with their own staff. The partner company never sees your customer price.
- Invoicing and controllingChecked hours become a draft invoice. You maintain the hourly rates at the site, at the customer, in a deal or on the order.
- AnalysisGroup and export hours across up to three levels. No monetary figures, deliberately.